Res Contractors Llc

  • Contact Person: Joel Landry
  • Contact Phone: 985-252-3400
  • Contact Email: jlandry@res-usa.net
  • Business Structure:
  • Corporate Entity (Not Tax Exempt)
  • Business Type:
  • Self Certified Small Disadvantaged Business
  • For Profit Organization
  • Limited Liability f
  • Industries Served: Highway, Street, and Bridge Construction, Other Heavy and Civil Engineering Construction, Electrical Contractors and Other Wiring Installation Contractors
  • Product Areas: EARTH MOVING AND EXCAVATING EQUIPMENT, EARTH MOVING & EXCAVATING EQ, CRANES AND CRANE-SHOVELS, MISCELLANEOUS CONSTRUCTION EQUIPMENT, MISC CONTRUCT EQ, ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER NON-BUILDING FACILITIES, CONSTRUCTION OF OFFICE BUILDINGS, CONSTRUCTION OF CONFERENCE SPACE AND FACILITIES, CONSTRUCTION OF SCHOOLS, CONSTRUCTION OF OTHER EDUCATIONAL BUILDINGS, CONSTRUCTION OF OTHER INDUSTRIAL BUILDINGS, CONSTRUCTION OF OTHER WAREHOUSE BUILDINGS, CONSTRUCTION OF OTHER NON-BUILDING FACILITIES

Sampling of Federal Government Funding Actions/Set Asides

In order by amount of set aside monies.

  • $67,659 - Monday the 27th of February 2012
    Department Of Army
    W07V ENDIST N ORLEANS
    TREATED TIMBER PILING
  • $56,500 - Monday the 14th of November 2011
    Department Of Army
    W07V ENDIST N ORLEANS
    STORM PROOFING PUMP STATIONS JSP-10 FAR 52.243-4 - CHANGES CIN-005 SWITCHGEAR CANOPIES MODIFY STEEL FOR M/B
  • $48,380 - Wednesday the 11th of January 2012
    Department Of Army
    W07V ENDIST N ORLEANS
    WBV, HPP, FRONTING PROTECTION AT ESTELLE NO. 2 PS, JEFFERSON PARISH, LA, MOD 1B, CIN-002 COMPACTED FILL ADJACENT TO HARVEY CANAL.
  • $476,000 - Wednesday the 25th of January 2012
    Department Of Army
    W07V ENDIST N ORLEANS
    WBV, HPP, FRONTING PROTECTION PROJECT AT ESTELLE NO. 2 PUMPING STATION, WBV-23, JEFFERSON PARISH, LA - CIN-004 DISCHARGE PIPE DELAYS (CLIN 0038)
  • $44,933 - Wednesday the 18th of January 2012
    Department Of Army
    W07V ENDIST N ORLEANS
    WBV, HPP, FRONTING PROTECTION PROJECT AT ESTELLE NO. 2 PUMPING STATION, WBV-23, JEFFERSON PARISH, LOUISIANA - CIN-005 PERPENDICULAR CUTOFF SHEETING
  • $44,225 - Monday the 13th of August 2012
    Department Of Army
    W07V ENDIST N ORLEANS
    WEST BANK AND VICINITY, HURRICANE PROTECTION PROJECT, FRONTING PROTECTION PROJECT AT ESTELLE NO. 2 PUMPING STATION, WBV-23, JEFFERSON PARISH, LOUISIANA AT JEFFERSON PARISH, LOUISIANA. MOD 1M, CIN-010 ADD ROADWAYS.
  • $43,911 - Tuesday the 20th of March 2012
    Department Of Army
    W07V ENDIST N ORLEANS
    DISCHARGE PIPE, FITTINGS, VALVES, FAR 52.211-18 VARIATION IN ESTIMATED QUANTITY VEQ-003 VAR IN EST QTY, CLIN 0017
  • $41,814 - Sunday the 26th of February 2012
    Department Of Army
    W07V ENDIST N ORLEANS
    TREATED TIMBER PILING
  • $36,305 - Thursday the 1st of December 2011
    Department Of Army
    W07V ENDIST N ORLEANS
    STORM PROOFING PUMP STATIONS JSP-10 FAR 52.243-4 - CHANGES CIN-006 DEFINITIZE CO-001 ADD FUEL OVERFLOW SYST
  • $3,354,943 - Tuesday the 13th of March 2012
    Department Of Army
    W07V ENDIST N ORLEANS
    DISCHARGE PIPE, FITTINGS, VALVES, FAR 52.211-18 VARIATION IN ESTIMATED QUANTITY VEQ-001 VARIATION IN EST QTY, CLIN 0005

© Copyright 2019
The Collier Report
published by 1918 Media LLC.
Information displayed in this dossier has been provided through available open source or public sources. No reliance should be made by readers or Collier Report subscribers. Funding actions are complicated and do not always represent dollar-for-dollar payments to vendors nor do they represent payments in certain instances. Requests for the modification of displayed information may be made to help.desk@1918.media.