The Collier Report of U.S. Government Contracting

Old School Reporting Using Modern Technology

Niking Corporation

  • Niking Corporation

  • View government funding actions
  • Wahiawa, HI 967862210
  • Phone:
  • Estimated Number of Employees: 55
  • Estimated Annual Receipts: $9,800,000
  • Business Start Date: 1982
  • Contact Person: Robert King
  • Contact Phone: 808-622-0443
  • Contact Email: bobk@nikingcorp.com
  • Business Structure:
  • Corporate Entity (Not Tax Exempt)
  • Business Type:
  • Minority Owned Business
  • For Profit Organization
  • Woman Owned Small Business
  • Woman Owned Business
  • Hispanic American Owned
  • Industries Served: Residential Remodelers, Commercial and Institutional Building Construction, Water and Sewer Line and Related Structures Construction, Power and Communication Line and Related Structures Construction, Highway, Street, and Bridge Construction, Other Heavy and Civil Engineering Construction, Structural Steel and Precast Concrete Contractors, Framing Contractors, Masonry Contractors, Roofing Contractors, Electrical Contractors and Other Wiring Installation Contractors, Plumbing, Heating, and Air-Conditioning Contractors, Drywall and Insulation Contractors, Flooring Contractors, Tile and Terrazzo Contractors, Finish Carpentry Contractors, Construction
  • Product Areas: UTILITIES- ELECTRIC, ELECTRIC SERVICES

Sampling of Federal Government Funding Actions/Set Asides

In order by amount of set aside monies.

  • $979,953 - Wednesday the 19th of September 2012
    Department Of Navy
    NAVFAC ENGINEERING COMMAND MARIANAS
    AJJY 12-1014 REPAIR BASE CHAPEL II IAW SOW AND CONTRACTOR'S PROPOSAL.
  • $78,749 - Tuesday the 6th of November 2012
    US Fish And Wildlife Service
    CONTRACTING AND GENERAL SERVICES DIV
    EAGLE CREEK REPAIR HATCHERY BLDG SEISMIC
  • $75,483 - Thursday the 12th of July 2012
    Department Of Navy
    NAVFAC ENGINEERING COMMAND HAWAII
    INSTALL PERMANENT (BELOW GROUND) IRRIGATION SYSTEM, PUULOA TRAINING FACILITY, OAHU, HI. MODIFICATION PROJECT: FY10 MCON P-182 MISSILE MAGAZINES, WEST LOCH, HI
  • $7,530 - Wednesday the 11th of July 2012
    Department Of Navy
    NAVFAC ENGINEERING COMMAND HAWAII
    ELECTRIAL REPAIRS, SUBSTATION 2, PCM X-05, INSTALL A SUMP PUMP IN EXISTING CABLE VAULT SUMP AND CONSTRUCT SEEPAGE PIT, BLDG. 820, MCBH
  • $75,228 - Friday the 13th of April 2012
    Department Of Navy
    NAVFAC ENGINEERING COMMAND HAWAII
    TO 0006, REPAIRS TO THIRD STREET, PCM X-04, REVISE DRAINLINE A IAW SKA-04, AND PCM X-05, REVISE DRAINLINE A STA 0+159 TO 0+174, MCBH
  • $7,500 - Tuesday the 26th of June 2012
    US Fish And Wildlife Service
    CONTRACTING AND GENERAL SERVICES DIV
    EAGLE CREEK REPAIR HATCHERY BLDG SEISMIC
  • $7,250 - Monday the 14th of November 2011
    Department Of Navy
    NAVFAC ENGINEERING COMMAND HAWAII
    REALIGN SECURITY FENCE FOR PUULOA RIFLE RANGE; CONSTRUCT 1,000 YARD RANGE ON RANGE "A" AT PUULOA TRAINING FACILITY, FY10 MCON (P-839), OAHU, HAWAII
  • $70,980 - Friday the 10th of July 2015
    Department Of Navy
    NAVFAC ENGINEERING COMMAND HAWAII
    TO ISSUED TO PROVIDE NEW SIDEWALKS ALONG 3RD STREET, INSTALL DRAINAGE IMPROVEMENTS FOR 3RD STREET, REPLACE THE 3RD STREET ROADWAY PAVEMENT STRUCTURE IN ITS ENTIRETY, AND INSTALL NEW TRAFFIC SIGNALS AT THE INTERSECTION OF 3RD STREET AND G STREET ON MCBH. MOD ISSUED TO RESOLVE UNFORESEEN ELECTRICAL CROSSING CONFLICT.
  • $6,739,442 - Friday the 10th of July 2015
    Department Of Navy
    NAVFAC ENGINEERING COMMAND MARIANAS
    1. THE FY12 GUAM STRIKE CLEAR WATER RINSE FACILITY AT ANDERSEN AIR FORCE BASE PROJECT IS FOR WORK REQUIRED IN THE DESIGN AND CONSTRUCTION OF A CLEAR WATER RINSE FACILITY CONSISTING OF A REINFORCED CONCRETE PUMPHOUSE, A 14 INCH REINFORCED CONCRETE PAD, A BELOW GROUND RINSE WATER SUPPLY TANK, A VALVE CONTROL BOX, AND A WASTE WATER SEDIMENTATION COLLECTION TANK. WORK INCLUDES ALL UTILITIES, SITE WORK (INCLUDING PAVEMENT DEMOLITION), A PUMP HOUSE VENTILATION SYSTEM, COMMUNICATIONS, AND A FIRE SUPPRESSION SYSTEM. THIS PROJECT WILL COMPLY WITH DOD ANTITERRORISM FORCE PROTECTION REQUIREMENTS PER UNIFIED FACILITIES CRITERIA. 2. THE CONTRACTOR SHALL FURNISH ALL DESIGN, LABOR, MATERIALS, EQUIPMENT, PERMIT AND CLEARANCES AND OTHER INCIDENTALS IN ACCORDANCE WITH THE REQUEST FOR PROPOSAL PACKAGE DATED 15 NOVEMBER 2011 FOR FY12 GUAM STRIKE CLEAR WATER RINSE FACILITY AT ANDERSEN AIR FORCE BASE, AMENDMENT 002 THERETO, AND NIKING CORPORATION S REVISED PROPOSAL DATED 3 MARCH 2012.
  • $63,154 - Thursday the 26th of April 2012
    Department Of Navy
    NAVFAC ENGINEERING COMMAND HAWAII
    OPTION 1

© Copyright 2019
The Collier Report
published by 1918 Media LLC.
Information displayed in this dossier has been provided through available open source or public sources. No reliance should be made by readers or Collier Report subscribers. Funding actions are complicated and do not always represent dollar-for-dollar payments to vendors nor do they represent payments in certain instances. Requests for the modification of displayed information may be made to help.desk@1918.media.