Sampling of Federal Government Funding Actions/Set Asides

In order by amount of set aside monies.

  • $90,264 - Wednesday the 11th of January 2012
    Public Buildings Service
    DESIGN AND CONSTRUCTION DIVISION
    THIS MODIFICATION IS BEING ISSUED TO REFLECT THE INCREASED HEAT LOAD IN ROOM MS-F4 AND IN THE SERVER ROOM.
  • $65,901 - Thursday the 1st of December 2011
    Public Buildings Service
    DESIGN AND CONSTRUCTION DIVISION
    THIS MODIFICATION IS BEING ISSUED TO FURNISH AND INSTALL TWO (2) COURTROOM LIFT ACCESSORS AS PER THE SCOPE OF WORK DATED 8/09/2011 FOR THE UNITED STATES FEDERAL COURTHOUSE LOCATED AT BAKERSFIELD, CA. THIS MODIFICATION IS IN THE AMOUNT OF $65,901.00 AS NEGOTIATED AND ACCEPTED AND NO TIME EXTENSION WILL BE ADDED TO COMPLETE THIS WORK. THE CURRENT TOTAL AMOUNT OF THIS CONTRACT IS $ 25,170,049.68.00.
  • $59,961 - Friday the 23rd of March 2012
    Public Buildings Service
    DESIGN AND CONSTRUCTION DIVISION
    THIS MODIFICATION IS BEING ISSUED TO REFLECT THE TELECOMMUNICATIONS PATHWAYS/SPACES AND COMMUNICATIONS BACKBONE CABLING.
  • $5,570 - Friday the 2nd of March 2012
    Public Buildings Service
    DESIGN AND CONSTRUCTION DIVISION
    THIS MODIFICATION IS BEING ISSUED TO REFLECT THE ART IN ARCHITECTURE SIGNAGE AND ARTWORK IDENTIFICATION AS PER THE SCOPE OF WORK DATED 1/17/2012 FOR THE U.S. FEDERAL COURTHOUSE LOCATED IN BAKERSFIELD, CA. THE SCOPE INCLUDES THE ARCHITECT'S EFFORTS IN DESIGNING THE ARTWORK NAMING PLATES AND THE VENDOR'S COST TO SUPPLY AND INSTALL THEM.
  • $500 - Wednesday the 13th of June 2012
    Public Buildings Service
    DESIGN AND CONSTRUCTION DIVISION
    *RECOVERY* NEW U.S. COURTHOUSE LOCATED IN BAKERSFIELD, CA NOT TO EXCEED / INSTALLATION OF TWO (2) WHIPS THIS MODIFICATION IS BEING ISSUED TO INSTALL TWO (2) WHIPS LOCATED ON THE SECOND FLOOR WEST SIDE CLERK OF THE COURT. THESE WHIPS ARE GOVERNMENT FURNISHED AND AVAILABLE FROM THE CONSTRUCTION MANAGER. THE CONTRACTOR IS DIRECTED TO PROCEED WITH THE INSTALLATION OF THE TWO (2) WHIPS AND IS DIRECTED TO SPEND UP TO $500.00 BUT NOT EXCEED $500.00 WITHOUT FURTHER DIRECTION FROM THE CONTRACTING OFFICER. THE CURRENT TOTAL AMOUNT OF THIS CONTRACT IS $25,324,679.25.
  • $4,889 - Wednesday the 11th of January 2012
    Public Buildings Service
    DESIGN AND CONSTRUCTION DIVISION
    THIS MODIFICATION IS BEING ISSUED TO REFLECT THE MILLWORK AND ELECTRICAL BOXES IN ROOM G15.
  • $41,433 - Monday the 4th of June 2012
    Public Buildings Service
    DESIGN AND CONSTRUCTION DIVISION
    THIS MODIFICATION IS BEING ISSUED TO REFLECT A SUMMARY OF ELEMENTS WHICH INCLUDE THE COURT SEALS, SIGNAGE, WEB CAMERAS, AND A CREDIT BACK TO GSA.
  • $4,000 - Friday the 2nd of March 2012
    Public Buildings Service
    DESIGN AND CONSTRUCTION DIVISION
    THIS MODIFICATION IS BEING ISSUED TO REFLECT THE RAHD AND ENERGY MODEL FEES COST FOR NBBJ/CONSULTANT'S TIME TO INPUT DATA INTO THE RAHD DATABASE, PV ANALYSIS, AND TO PROVIDE USGBC DOCUMENT SUPPORT FOR LEED ENERGY REPORTS AS PER THE SCOPE OF WORK DATED 1/24/2012 FOR THE U.S FEDERAL COURTHOUSE IN BAKERSFIELD, CA.
  • $245,748 - Friday the 23rd of March 2012
    Public Buildings Service
    DESIGN AND CONSTRUCTION DIVISION
    THIS MODIFICATION IS BEING ISSUED TO REFLECT THE CABLING FOR DATA AND TELEPHONE, AUDIO AND VIDEO FOR COURT OPERATIONS AND OPTIONS FOR VIDEO CONFERENCING AND PROBATION VIDEO.
  • $21,707 - Wednesday the 11th of January 2012
    Public Buildings Service
    DESIGN AND CONSTRUCTION DIVISION
    THE PURPOSE OF THIS MODIFICATION WAS TO ISSUE THE ATT VAULT, PG&E POLE, AND THE STORM WATER POLLUTION PLAN APPLICATION FEE.

© Copyright 2019
The Collier Report
published by 1918 Media LLC.
Information displayed in this dossier has been provided through available open source or public sources. No reliance should be made by readers or Collier Report subscribers. Funding actions are complicated and do not always represent dollar-for-dollar payments to vendors nor do they represent payments in certain instances. Requests for the modification of displayed information may be made to help.desk@1918.media.